Friday, April 19, 2024

Featured Video

Latest Stories

Top 10 Music

Upcoming Events

Zomba City Festival

Fri, 26 Apr 2024 10:00:00 UTC @ Botanic Garden - 2024 Zomba City Festival is schedulled to take place on 26 to 28 April at Botanic Garden in Zomba This is a festival for all ages in the historic mountain city of Zomba. Celebrate Cultu... More Info
Njuchi Day

Sat, 27 Apr 2024 10:00:00 UTC @ New Village House (Kampala Manase) - Elinationa And No Limit Presents Njuchi Day Music show with Njuchi Zitatu. The show will take place at New Village House in Manase on 27 April 2024 and it will have music performances b... More Info

Govt cuts scope of Chipembere Highway project

The Chipembere Highway construction will not reach Illovo roundabout in Limbe as initially planned because the cost of the project has soared, Minister of Transport and Public Works Sidik Mia has said.

Speaking to journalists in Blantyre after inspecting the project, Mia said works on the road will only cover 2.7km, from Chichiri roundabout to Yiannakis roundabout in Limbe.

Initially the project was planned to cover over 4km, from the Chichiri roundabout to Illovo roundabout at the cost of about US $11 million.

Mia said the money is no longer enough to finish the whole project.

“The scope of work has been reduced due to escalating costs. As you know work stalled for a long time due to fuel, cement and forex shortage that was being experienced last year,” Mia said.

Roads Authority and Blantyre City Council officials said current estimations show that up to US$7 million will be spent on works from Chichiri roundabout to Yiannakis roundabout.

The balance, the officials said, would not be sufficient to cover the stretch from Yiannakis to Illovo because that is the most complicated stretch.

Japanese contractor Nippo Corporation is implementing the project.

Subscribe to our Youtube Channel:

Related Posts

3 COMMENTS

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Popular Articles