Salima solar project ends April 2021

Representatives of JMC Power have indicated that construction of a solar farm in Salima which is expected to add 60 megawatts (MW) of electricity to the national grid will be complete by April 2021.

This came out when Minister of Energy, Newton Kambala, visited the project site recently to appreciate the progress made.

It has transpired that the project missed its deadline early this year due to travel restrictions that deter engineers from installing solar panels and transformers under the project.

JCM Power Country Director, Phylip Leferink, said the company acquired 228,000 solar panels to be installed on the farm.

“Apart from solar panels we also have 34 big transformers that we intend to plant in various areas to support power from the farm. All we need is support for the project to be successful. So far the community around us has been so helpful and we have created about 300 jobs for the local community in our company,” Leferink said.